Housing , hotel and office complex Esterhazyplatz Eisenstadt

Project data

Construction period: 10 / 2020 – 08 / 2021 Contractor: STEINER

Housing Complex
1600 Tons

Project in the heart of Eisenstadt

In the center of Eisenstadt, BEST supplied and layed reinforcement for a large project consisting of a hotel, shops, offices and residential space. Many installation sites had to be served simultaneously in a short period of time to meet the tight schedule.

The project posed a challenging task due to a weak caliber distribution and a high number of wall reinforcements. The use of many man-hours required a lot of coordination work by the BEST laying supervisor, in order to support an almost seamless construction process.

© BEST – Baueisen- und Stahl – bearbeitungsgesellschaft m.b.H.